Mixing System Alterations
CASE STUDY - Mixing System Alterations (value $30,000)
Situation
Large Stockfeed mill in Toowoomba
Task
Mixer alterations to improve production of Stockfeed
Actions
- Obtain customers initial requirements
- This included manufacture and installation of fabricated products including bins and access platforms and handrails
- Detail the customer’s requirements as well as a manufacturing procedure and installation procedure.
- From the procedure it can be determined the practicality of the project
- Once the practicality has been sorted a timeline is produced
- The customer was consulted and any problems determined and solved
- A quote is prepared and submitted
- Manufacture drawings prepared
- Parts manufactured
- Installation
- This project required organisation between the customer, electrical people, crane hire people (100 tonne crane required for this job).
Results
- Within customers budget
- We were able to offer alternatives to meet the budget and there the project go ahead
- The mixing is much more efficient now
- Area is more safe